DESIGNERS of factories:
CONFECTIONERY FACTORY
§
Main Designer: Petar Milovanovic, BSc (arch.)
§
Main Designer of Technology: Milutin Ivanovic, BSc
(technology)
§
Other Main Designers:
- Civil Engineering Structures: Sava Parezanovic, BSc (civil
eng) and Arsa Simov, BSc (civil eng)
- Water Supply and Sewage Installations: Mirjana
Milovanovic, BSc (arch)
- Thermal Installations: Goran Stankovic, BSc (mech. eng.)
- Electricity Installations: Milutin Ilincic, BSc
(electr)
WRAPPING AND PACKING MATERIAL FACTORY
§
Main Designer: Vidoje Veljkovic, BSc (civil eng.)
- Main Designer of Technology: Djordje Askovic, BSc
(technology)
- Technology Coordinator: Milovan Aleksic, BSc (technology)
- Main Designer for Civil Engineering Structures: Slobodan
Jovanovic, BSc (civil eng. )
- Architectural part: Miroslav Jovovic, BSc (arch.)
- Electrical Installations: Dragoljub Djuric, BSc
(electr)
- Mechanical Installations: Bozidar Letunica, BSc (mech.
eng.)
- Hydrotechnical Installations: Slobodan Stefanovic, BSc
MILK RECEIVING AND PROCESSING FACTORY
§
Main Designer: Vidoje Veljkovic, BSc (civil eng.)
- Main Designer of Technology: "PKB IMLEK", Gordana
Dolenc, BSc (technology)
- Technology Coordinator: Milovan Aleksic, BSc (technology)
- Civil Engineering Structures: Slobodan Jovanovlc, BSc (civil
eng.)
- Architectural fart: Djordje Kanjo, BSc (arch.)
- Electrical Installations: Zvonko Bicenko, BSc
- Mechanical Installations: B. Letunica, BSc (mech. eng.)
- Hydrotechnical Installations: Zoran Krstic, BSc
FROZEN FOOD AND ICE CREAM FACTORY
§
Main Designer: Petar Milovanovic, BSc (arch.)
- Main Designer of Technology: Ljubomir Kupresanin, BSc
(technology)
- Civil Engineering Structures: Arsa Simov, BSc (civil
eng)
- Water Supply and Sewage Installations: Zorica
Milovanovic, BSc (civil eng.)
- Thermo-technical Installations: Goran Stankovic, BSc
(mech eng)
- Electrical Installations: Milutin llincic, BSc (electr.)
- Cooling Installations: Slobodan Grujic, BSc (mech. eng.)
INFRASTRUCTURE FACILITIES
§
Main Designer: Vidoje Veljkovic, BSc (civil eng.)
- Main Designer for Civil Engineering Structures: Bogoljub
Goloskokovic, BSc (civil eng.)
- Mechanical Installations: Bozidar Letunica, BSc (mech. eng.)
- Electrical Installations: Dragan llic, BSc (electr)
- Hydrotechnical Installations: Zoran Krstic, BSc
§
Description of the project: The complex of factories within
the Kuban Combine includes 4 newly built factories on the area of
320 ha, a housing estate "Sadvod", and infrastructure for the
industrial complex:
- Confectionery Factory;
- Wrapping and Packing Material Factory;
- Milk Receiving and Processing Factory;
- Frozen Food and Ice Cream Factory.
CONFECTIONERY FACTORY
§
The building is constructed from prefabricated elements, with
the area 23,000 m2. Height of the building 8 m. The structure
is of prefabricated reinforced concrete pillars, adhesively
prestressed
beams span 18 m, roof slabs span 12 m, and as facade elements
prefabricated facade panels of ceramsite concrete.
WRAPPING AND PACKING MATERIAL FACTORY
§
It is the biggest building within the complex with the area
50,000 m2. The building is partly one-floor and partly
two-floor. The capacity of the factory is 22,000 t per year.
MILK RECEIVING AND PROCESSING FACTORY
§
From the technological point of view, it is a modern building
with area 14,000 m2 and yearly capacity of 52,000,000
l.
§
Within the dairy there are: receiving and pasterization of
milk, curdled milk products, butter, sterilized milk. All the
processes are automatic, applying the most modern processing technique.
FROZEN FOOD AND ICE CREAM FACTORY
§
The building consists of three technological units, with
total area 20,000 m2.
§
THE HOUSING SETTLEMENT "SADVOD" includes houses for
staff accommodation, as well as the hotel, clinic, and shopping
& crafts centre.
INFRASTRUCTURE
§
There have been built: water supply, rain and waste water
sewage, steam, hot water and gas distribution, electrical cable
distribution, roads and footways.
|