Designed by: DBR "Velika Morava"
Main Designer and Coordinator V. Petrovic, BSc (civil eng.)
Processing by:
1. ZOVP "Morava" - Water Resources Engineering
Co. and
2. Institute for Water Management "Jaroslav Cerni"
Main Contractor: DBR "Velika Morava"
Main Sub-contractors The United Water Management Organizations
of Serbia (region of this river basin):
"Srbijavode", "Erozija",
"Zapadna Morava", "Erozija",
VP "Smederevo", "Erozija", DD za
vodoprivredu i hidrogradnju (Water Management and Hydroengineering Co.), DD
za vodoprivredu (Water Management Co.), "Morava, Hidrogradnja i
erozija (Hydroengineering and Erosion), VP
Cuprija; DVH Palanka, "Niskogradnja", "Ibar-Lepenac", Institute for Water Management
"Jaroslav Cerni"
Purpose of the Project: Regulation of the Velika Morava river
basin
Years of Construction: 1960-1995
|
|
THE TOTAL AREA of the Morava river basin is 37,966
km2. Out of this the Zapadna Morava river basin is 15,750
km2; the Juzna Morava river basin is 15,466
km2; the Velika Morava river basin is 6,770
km2. The purpose of control and
development of the river basin is in the construction
of buildings and other works to improve the canter regime in the river basin as well as
the landscaping to protect it. The improvement of the water
regime cowers the following by regulating the waters the damage
which is done to the land is decreased as well as to the
building and other property within the river basin. The stabilization of
water regime is one of the conditions for economic water
management and economic development.
§
In order to regulate the river basin the following works have
been performed flood protection and river
regulation; drainage; flood control and deposit control by means of accumulation;
counter-erosion works; supply of water for industry needs.
§
In the Morava river basin, in the lowlands, 225,000 ha is
endangered by river water flooding out of which about 112,000 ha
only in the Velika Morava river basin. The biggest scope of
work were executed in the places where the flooding areas were the
Iargest calculated according to the linear kilometer of
embankment .
The regulation of the Velika Morava river basin and its
tributaries included the following works:
- stream regulation 1,320 ha;
- embankment building 2,015 km;
- regulation structures 1,376 km;
- large accumulations 10 Km
- small and medium accumulations 48 km;
- improvement of agricultural land 44,500 ha;
- construction of water supply 1,430 km;
- construction of sewage;
- counter-erosion works 6,000 ha;
- construction of fish ponds 3,900 ha.
§
For the stabilization and improvement of the Velika Morava
river basin and its tributaries the following has been done
during the last ten years:
- irrigation system in the area of Zabari coffer - 8,300 ha;
- drainage system in the districts of Svilajnac and Despotovac
5,000 ha;
- drainage system in the district of Batocina (Badnjenac) 430
km
- drainage system in the area of Kusiljevacka coffer 1,800 km;
- drainage system in the district of Malo Crnice 2500 ha.
- regulations of the Resava river upstream 26 km
from Svilajnac
- regulation of the Jablanica river in the district of Leskovac
16 km;
- accumulation and dam Prvonek;
- accumulation and dam Barje;
- accumulation and dam Selova.
|